Formwork System Inspection & Test Plan

ITP for formwork system erection covering design certification, prop loading, shore spacing, alignment verification, safety provisions and striking criteria per AS 3610.

13 checklist items
2 hold points
Use this template — it's free

Checklist Preview

Design & Documentation

Requires sign-off
P/F
Formwork design certified by engineer
Hold
Safe work method statement reviewed
P/F
Formwork materials in serviceable condition

Erection & Alignment

Requires sign-off
P/F
Base plates on adequate bearing surface
P/F
Shore spacing per formwork drawings
Hold
P/F
Props plumb and braced
P/F
Camber provision per engineer specification
P/F
Bearer and joist spacing compliant
P/F
Deck sheets free from damage and gaps

Safety & Striking

Requires sign-off
P/F
Edge protection installed at all open edges
P/F
Safe access provided to all work areas
P/F
Striking criteria defined and documented
#
Minimum stripping strength requirement (MPa)

Prefer AI?

Generate a custom Concrete ITP in seconds

Describe your scope and our AI builds a complete ITP with hold points, witness points, and sign-off roles — tailored to your project.

Free AI ITP Generator →

Ready to use this template?

Sign up, import this ITP template into your project, and start inspecting. 14 days free — no credit card required.

Get started free