Ground Slab Inspection & Test Plan

ITP for residential and commercial ground floor slabs covering subgrade preparation, vapour barrier, reinforcement, joint layout, concrete placement and flatness tolerances per AS 3600 and AS 2870.

13 checklist items
3 hold points
1 witness points
Use this template — it's free

Checklist Preview

Subgrade Preparation

Requires sign-off
P/F
Subgrade compacted to 95% MDD
Hold
P/F
Fill material per specification
P/F
Termite treatment applied per specification
P/F
Vapour barrier installed and lapped correctly

Reinforcement & Joints

Requires sign-off
P/F
Reinforcement type and size per structural drawings
Hold Witness
P/F
Bar chairs maintaining correct cover
P/F
Edge rebate and beam formwork set
P/F
Control joint layout per structural design

Concrete Placement

Requires sign-off
P/F
Concrete grade and slump per specification
P/F
Placement method minimising segregation
P/F
Floor flatness/levelness (FF/FL) per specification
Hold
P/F
Curing commenced within specified timeframe
P/F
Control joints cut within 24 hours

Prefer AI?

Generate a custom Concrete ITP in seconds

Describe your scope and our AI builds a complete ITP with hold points, witness points, and sign-off roles — tailored to your project.

Free AI ITP Generator →

Ready to use this template?

Sign up, import this ITP template into your project, and start inspecting. 14 days free — no credit card required.

Get started free