Concrete Post-Pour Inspection & Test Plan
Post-pour inspection ITP covering curing regime, formwork stripping, surface finish assessment, dimensional checks and compressive strength test results per AS 3600.
12 checklist items
3 hold points
1 witness points
Checklist Preview
Curing
Requires sign-offP/F
Curing method as specified (compound/water/membrane)P/F
Curing commenced within specified timeframe Hold
P/F
Minimum curing duration maintainedP/F
Ambient temperature during curing recordedFormwork Stripping
Requires sign-offP/F
Minimum stripping strength achieved Hold Witness
P/F
No damage observed on formwork removalP/F
Reshoring installed where requiredQuality Assessment
Requires sign-offP/F
Surface finish meets class requirementP/F
No honeycombing or voids observedPhoto
P/F
Dimensional tolerances within AS 3600 limitsP/F
Crack assessment satisfactory#
28-day compressive strength result (MPa) Hold
Prefer AI?
Generate a custom Concrete ITP in seconds
Describe your scope and our AI builds a complete ITP with hold points, witness points, and sign-off roles — tailored to your project.
Free AI ITP Generator →Ready to use this template?
Sign up, import this ITP template into your project, and start inspecting. 14 days free — no credit card required.
Get started free