Post-Tensioning Inspection & Test Plan

ITP for bonded and unbonded post-tensioning systems covering tendon profiling, anchor zone reinforcement, stressing operations, elongation checks and grouting per AS 3600.

15 checklist items
4 hold points
2 witness points
Use this template — it's free

Checklist Preview

Tendon Installation

Requires sign-off
P/F
Tendon profile per PT drawings
Hold
P/F
Tendon spacing compliant
P/F
Anchorage hardware correctly installed
P/F
Duct integrity verified (no damage)
P/F
Anchor zone reinforcement per design
Hold

Stressing Operations

Requires sign-off
P/F
Minimum concrete strength for stressing achieved
Hold Witness
P/F
Jack calibration certificate current
P/F
Stressing sequence per engineer specification
P/F
Elongation within ±7% of calculated
Hold
#
Measured elongation (mm)
P/F
Lock-off force recorded

Grouting (Bonded System)

Requires sign-off
P/F
Grout mix design per specification
P/F
Grout injection continuous from low to high point
Witness
P/F
Grout cube strength satisfactory
P/F
Anchor pocket filled and sealed