DemolitionCommercial
Services Disconnection Inspection & Test Plan
ITP for pre-demolition services disconnection covering electrical isolation, gas capping, water disconnection, sewer capping, data removal and authority notifications.
13 checklist items
3 hold points
1 witness points
Checklist Preview
Authority Notifications
Requires sign-offP/F
Electricity authority disconnection confirmed Hold
P/F
Gas authority disconnection/capping confirmed Hold
P/F
Water authority disconnection confirmedP/F
Telecommunications provider notified and disconnectedSite Isolation
Requires sign-offP/F
Main switchboard de-energised and locked off Hold
P/F
Gas meter removed or capped at mainP/F
Water supply capped at boundaryP/F
Sewer connection capped at boundaryP/F
Stormwater connections noted for future workVerification
Requires sign-offP/F
Dead test on all electrical circuits Witness
P/F
Gas line pressure confirmed at zero✓
All disconnection certificates receivedAa
Service disconnection register referenceReady to use this template?