Earthing & Lightning Protection Inspection & Test Plan
ITP for building earthing systems and lightning protection covering earth electrode installation, bonding conductors, earth resistance testing and lightning rod placement per AS/NZS 3000 and AS 1768.
12 checklist items
2 hold points
1 witness points
Checklist Preview
Earth Electrode System
Requires sign-offP/F
Electrode type and burial depth per design#
Earth resistance (Ω) Hold
P/F
Electrode connections exothermically weldedPhoto
P/F
Ring earth continuity verifiedBonding Conductors
Requires sign-offP/F
Main earth bar connections verified Hold Witness
P/F
Structural steel bonding completeP/F
Water pipe bonding connectedP/F
Bonding conductor sizing per AS/NZS 3000Lightning Protection
Requires sign-offP/F
Air terminal placement per risk assessmentP/F
Down conductor routing and fixings compliantP/F
Test joints accessible and labelledP/F
SPD coordination across zonesReady to use this template?