Switchboard Installation Inspection & Test Plan
Comprehensive ITP for main and distribution switchboard installation including bus-bar connections, circuit breaker coordination, arc fault containment and labelling compliance per AS/NZS 3000 and AS/NZS 61439.
16 checklist items
3 hold points
1 witness points
Checklist Preview
Physical Installation
Requires sign-offP/F
Switchboard mounting plumb and levelP/F
Seismic restraints installed where requiredP/F
Working clearance zones maintainedP/F
Ventilation clearances per manufacturerP/F
Cable entry glands correctly fittedInternal Wiring & Connections
Requires sign-offP/F
Bus-bar connection torque values verified Hold Witness
P/F
Phase rotation correct (L1-L2-L3) Hold
P/F
Neutral bar connections secureP/F
Internal cable dressing neat and compliantP/F
Arc fault containment rating verifiedProtection & Coordination
Requires sign-offP/F
Protection coordination study reviewed Hold
P/F
CT ratios verified per metering specP/F
Surge protection device installedLabelling & Documentation
P/F
Circuit directory completed and affixedP/F
Danger and warning labels affixed✓
As-built single-line diagram providedPrefer AI?
Generate a custom Electrical ITP in seconds
Describe your scope and our AI builds a complete ITP with hold points, witness points, and sign-off roles — tailored to your project.
Free AI ITP Generator →Ready to use this template?
Sign up, import this ITP template into your project, and start inspecting. 14 days free — no credit card required.
Get started free