Shoring & Retention System Inspection & Test Plan
ITP for temporary shoring and earth retention systems covering sheet piling, soldier pile walls, shotcrete, ground anchors and deflection monitoring for deep excavations.
13 checklist items
3 hold points
2 witness points
Checklist Preview
Design & Documentation
Requires sign-offP/F
Shoring design certified by geotechnical engineer Hold
P/F
Construction sequence plan reviewedP/F
Monitoring plan establishedInstallation
Requires sign-offP/F
Piles installed to design depth and alignment Hold Witness
P/F
Walers and struts installed per staging planP/F
Shotcrete thickness and mix per specificationP/F
Ground anchors installed and proof-tested Hold
#
Anchor proof test load (kN)Monitoring & Performance
Requires sign-offP/F
Inclinometer readings within design limitsP/F
Survey monitoring of adjacent structures Witness
P/F
Groundwater level below formation#
Maximum wall deflection (mm)P/F
Trigger levels reviewed and currentPrefer AI?
Generate a custom Excavation ITP in seconds
Describe your scope and our AI builds a complete ITP with hold points, witness points, and sign-off roles — tailored to your project.
Free AI ITP Generator →Ready to use this template?
Sign up, import this ITP template into your project, and start inspecting. 14 days free — no credit card required.
Get started free