Fire Hydrant System Inspection & Test Plan
ITP for building fire hydrant systems covering pipework, hydrant valve installation, booster assembly, flow and pressure testing per AS 2419.1 and authority requirements.
12 checklist items
3 hold points
2 witness points
Checklist Preview
Pipework
Requires sign-offP/F
Pipe material and rating per AS 2419.1P/F
Pipe routing per hydraulic designP/F
Isolation valves at required locationsP/F
Fire-rated penetration sealing Hold
Hydrant Valves & Landing Valves
Requires sign-offP/F
Hydrant valve height per AS 2419.1P/F
Hydrant signage and marking installedP/F
Landing valves accessible in stair pressurisation zoneBooster Assembly & Testing
Requires sign-offP/F
Booster assembly per AS 2419.1 detail Hold
P/F
Hydrostatic test satisfactory Hold Witness
P/F
Flow and pressure test at most remote hydrant Witness
P/F
Fire brigade connection approved✓