Fire Sprinkler System Inspection & Test Plan
ITP for automatic fire sprinkler systems covering pipework installation, head placement, hydraulic testing, alarm valve operation and system commissioning per AS 2118.
13 checklist items
2 hold points
2 witness points
Checklist Preview
Pipework Installation
Requires sign-offP/F
Pipe material and class per specificationP/F
Pipe hanger spacing per AS 2118P/F
Seismic bracing installed per NZS 4219P/F
Branch line spacing per designSprinkler Heads
Requires sign-offP/F
Head type and temperature rating correct Hold
P/F
Deflector-to-ceiling distance per AS 2118P/F
Head coverage area within maximum spacingP/F
Obstruction clearance rules satisfiedTesting & Commissioning
Requires sign-offP/F
Hydrostatic test at 1400kPa for 2 hours Hold Witness
P/F
Alarm valve operation satisfactoryP/F
Flow switch activating fire panel Witness
P/F
Main drain test flow satisfactory✓
Block plan installed at alarm valveReady to use this template?