Fire Sprinkler System Inspection & Test Plan

ITP for automatic fire sprinkler systems covering pipework installation, head placement, hydraulic testing, alarm valve operation and system commissioning per AS 2118.

13 checklist items
2 hold points
2 witness points
Use this template — it's free

Checklist Preview

Pipework Installation

Requires sign-off
P/F
Pipe material and class per specification
P/F
Pipe hanger spacing per AS 2118
P/F
Seismic bracing installed per NZS 4219
P/F
Branch line spacing per design

Sprinkler Heads

Requires sign-off
P/F
Head type and temperature rating correct
Hold
P/F
Deflector-to-ceiling distance per AS 2118
P/F
Head coverage area within maximum spacing
P/F
Obstruction clearance rules satisfied

Testing & Commissioning

Requires sign-off
P/F
Hydrostatic test at 1400kPa for 2 hours
Hold Witness
P/F
Alarm valve operation satisfactory
P/F
Flow switch activating fire panel
Witness
P/F
Main drain test flow satisfactory
Block plan installed at alarm valve

Prefer AI?

Generate a custom Fire Protection ITP in seconds

Describe your scope and our AI builds a complete ITP with hold points, witness points, and sign-off roles — tailored to your project.

Free AI ITP Generator →

Ready to use this template?

Sign up, import this ITP template into your project, and start inspecting. 14 days free — no credit card required.

Get started free