ITP for formwork systems supporting post-tensioned concrete slabs covering design for PT loads, stressing end clearances, strand deflection support and re-propping after stressing per AS 3610.
12 checklist items
3 hold points
1 witness points
Checklist Preview
Design for PT Loads
Requires sign-offP/F
Formwork design accounts for PT loading Hold
P/F
Stressing end pocket formwork positionedP/F
Strand deflection support chairs at correct spacingP/F
Dead end anchorage blockouts formedErection
Requires sign-offP/F
Soffit level set with camber per engineerP/F
Prop load capacity verified for PT slab weight Hold
P/F
Edge forms allow stressing jack accessP/F
Pour strip formwork installed where specifiedStripping & Re-propping
Requires sign-offP/F
Stressing completed before strip approval Hold Witness
P/F
Strip sequence per engineer instructionP/F
Re-propping installed per structural requirementsP/F
Re-propping duration per engineer specificationReady to use this template?