FormworkIndustrial
Precast Formwork & Mould Inspection & Test Plan
ITP for precast concrete moulds and formwork covering mould fabrication, dimensional tolerances, release agent application, insert placement and demoulding procedures.
11 checklist items
3 hold points
1 witness points
Checklist Preview
Mould Fabrication
Requires sign-offP/F
Mould dimensions per production drawings Hold
P/F
Mould surface finish suitable for required classP/F
Side rails or magnetic formwork alignedPre-Pour
Requires sign-offP/F
Release agent uniformly appliedP/F
Cast-in inserts positioned per drawing Hold Witness
P/F
Lifting anchors at correct position and depthP/F
Reinforcement cover verified with spacersDemoulding & Handling
Requires sign-offP/F
Minimum demoulding strength achieved Hold
P/F
Demoulding procedure followed without damageP/F
Element marked with ID and orientationP/F
Stored on appropriate dunnage and supportsPrefer AI?
Generate a custom Formwork ITP in seconds
Describe your scope and our AI builds a complete ITP with hold points, witness points, and sign-off roles — tailored to your project.
Free AI ITP Generator →Ready to use this template?
Sign up, import this ITP template into your project, and start inspecting. 14 days free — no credit card required.
Get started free