Slip Form Inspection & Test Plan

ITP for slip-form concrete construction covering form design, jacking system, reinforcement placement, concrete supply continuity and verticality monitoring for silos, cores and towers.

12 checklist items
3 hold points
2 witness points
Use this template — it's free

Checklist Preview

Slip Form Setup

Requires sign-off
P/F
Form panels assembled and aligned
P/F
Jack rods installed and tested
Hold
P/F
Jack synchronisation verified
P/F
Work platforms and safety harness points installed

Continuous Pour Operations

Requires sign-off
P/F
Concrete supply continuity plan confirmed
Hold
P/F
Lift rate maintained per specification
P/F
Reinforcement placed ahead of rising form
Witness
P/F
Embedments placed at correct elevations

Quality Monitoring

Requires sign-off
P/F
Verticality within tolerance (plumb bob/laser)
Hold Witness
P/F
Wall thickness measured and within tolerance
P/F
Early age strength monitoring satisfactory
P/F
Surface defects repaired progressively

Prefer AI?

Generate a custom Formwork ITP in seconds

Describe your scope and our AI builds a complete ITP with hold points, witness points, and sign-off roles — tailored to your project.

Free AI ITP Generator →

Ready to use this template?

Sign up, import this ITP template into your project, and start inspecting. 14 days free — no credit card required.

Get started free