HVAC System Commissioning Inspection & Test Plan

ITP for final HVAC commissioning covering air and water balancing, temperature control verification, noise measurements, performance validation and handover documentation per AIRAH guidelines.

13 checklist items
2 hold points
2 witness points
Use this template — it's free

Checklist Preview

Air Side Balancing

Requires sign-off
P/F
Supply air volumes within ±10% of design
Hold
P/F
Return and exhaust air balanced
P/F
Outside air minimum per AS 1668.2
P/F
Diffuser throw and velocity per selection

Water Side Balancing

Requires sign-off
P/F
Chilled water flow rates per design
P/F
Condenser water flow rates per design
P/F
Pump head and flow at duty point
Witness
P/F
Balancing valve settings recorded

Performance Validation

Requires sign-off
P/F
Room temperatures within design band
Hold Witness
P/F
Humidity control within specification
P/F
Noise levels within NC rating
Aa
TAB report reference number
P/F
Outstanding defects listed for rectification

Prefer AI?

Generate a custom HVAC ITP in seconds

Describe your scope and our AI builds a complete ITP with hold points, witness points, and sign-off roles — tailored to your project.

Free AI ITP Generator →

Ready to use this template?

Sign up, import this ITP template into your project, and start inspecting. 14 days free — no credit card required.

Get started free