HVACCommercial
HVAC System Commissioning Inspection & Test Plan
ITP for final HVAC commissioning covering air and water balancing, temperature control verification, noise measurements, performance validation and handover documentation per AIRAH guidelines.
13 checklist items
2 hold points
2 witness points
Checklist Preview
Air Side Balancing
Requires sign-offP/F
Supply air volumes within ±10% of design Hold
P/F
Return and exhaust air balancedP/F
Outside air minimum per AS 1668.2P/F
Diffuser throw and velocity per selectionWater Side Balancing
Requires sign-offP/F
Chilled water flow rates per designP/F
Condenser water flow rates per designP/F
Pump head and flow at duty point Witness
P/F
Balancing valve settings recordedPerformance Validation
Requires sign-offP/F
Room temperatures within design band Hold Witness
P/F
Humidity control within specificationP/F
Noise levels within NC ratingAa
TAB report reference numberP/F
Outstanding defects listed for rectificationReady to use this template?