Playground Softfall Installation Inspection & Test Plan
ITP for playground impact-attenuating surfaces covering subgrade preparation, drainage, rubber wet-pour or synthetic grass installation, fall height compliance and certification per AS 4422.
13 checklist items
3 hold points
1 witness points
Checklist Preview
Subgrade & Drainage
Requires sign-offP/F
Subgrade excavated to correct depth and gradedP/F
Drainage provisions installedP/F
Subgrade compacted and stableP/F
Edge containment installed and secureSoftfall Installation
Requires sign-offP/F
Softfall type per specification (wet-pour/tiles/grass)P/F
Base layer (SBR) thickness per fall height chart Hold
P/F
Top layer colour and EPDM grade per specificationP/F
Total thickness per critical fall height Hold
P/F
Seams bonded with no gaps or liftingTesting & Certification
Requires sign-offP/F
HIC (Head Injury Criterion) test satisfactory per AS 4422 Hold Witness
P/F
Surface draining with no pondingP/F
Softfall integrated with equipment footingsAa
Impact attenuation test certificate referenceReady to use this template?