Water Supply Pipework
Requires sign-offP/F
Pipe material and grade per specificationP/F
Pipe support spacing compliantP/F
Hot water pipe insulation installedP/F
Pressure test at 1500kPa for 30 minutes Hold Witness
P/F
Backflow prevention devices installedWaste & Vent Piping
Requires sign-offP/F
Pipe falls per AS/NZS 3500.2 (1:40 min)P/F
Traps installed at all fixture pointsP/F
Vent pipe termination height compliantP/F
Air admittance valves where permittedP/F
Drain tested with water to full bore Hold
Fixture Point Positions
P/F
Basin rough-in heights per drawingP/F
Toilet set-out dimensions verifiedP/F
Shower waste position correctP/F
Hose cock positions per specificationReady to use this template?