Membrane Roofing Inspection & Test Plan
ITP for single-ply or built-up membrane roofing systems covering substrate preparation, membrane laying, seam welding, penetration detailing and drainage verification per AS 4654.1.
13 checklist items
3 hold points
1 witness points
Checklist Preview
Substrate Preparation
Requires sign-offP/F
Substrate dry, clean and free from protrusionsP/F
Falls to drainage outlets per design Hold
P/F
Vapour barrier installed where specifiedP/F
Insulation boards laid and securedMembrane Installation
Requires sign-offP/F
Membrane type and thickness per specificationP/F
Hot air weld temperature per manufacturerP/F
Seam integrity test (probe or vacuum) Hold Witness
P/F
Overlap width per manufacturer minimumP/F
Mechanical fixing pattern per wind uplift zoneDetails & Completion
Requires sign-offP/F
Upstand at walls and parapets per detailP/F
Penetration boots welded and sealedPhoto
P/F
Drainage outlet collars clamped and sealedP/F
Flood or electronic leak test satisfactory Hold
Ready to use this template?
Sign up for free, import this ITP template into your project, and start inspecting. Your first project is always free.