Metal Decking (Bondek) Installation Inspection & Test Plan
ITP for composite metal deck (Bondek/Condeck) installation as permanent formwork and reinforcement for concrete slabs covering sheet orientation, end laps, propping, shear stud welding and edge trim.
12 checklist items
2 hold points
1 witness points
Checklist Preview
Deck Sheet Laying
Requires sign-offP/F
Deck profile and gauge per structural specificationP/F
Sheet rib orientation per structural drawingsP/F
End laps positioned over supporting steelP/F
Deck fixed to steel with self-drilling screwsPropping & Shear Studs
Requires sign-offP/F
Propping centres per manufacturer span tables Hold
P/F
Shear studs welded through deck per specification Hold Witness
P/F
Stud bend test satisfactory (1 in 20)P/F
Stud height after welding verifiedEdge Trim & Penetrations
Requires sign-offP/F
Edge trim and closure pieces installedP/F
Penetration reinforcement per structural designP/F
Top mesh and additional reinforcement placedP/F
Deck surface clean prior to concrete pourReady to use this template?