Structural Steel Erection Inspection & Test Plan
ITP for on-site erection of structural steelwork covering crane operations, temporary bracing, alignment, plumb checks and connection completion per AS 4100.
13 checklist items
3 hold points
2 witness points
Checklist Preview
Pre-Erection Checks
Requires sign-offP/F
Erection sequence plan reviewedP/F
Base plates and anchor bolts surveyed Hold
P/F
Grout bed levels set to toleranceP/F
Members identified and match delivery scheduleErection Process
Requires sign-offP/F
Crane lift plan approvedP/F
Temporary connections securing membersP/F
Column plumb within H/500 tolerance Hold Witness
P/F
Beam levels within ±5mm toleranceP/F
Temporary bracing installed per planPermanent Connections
Requires sign-offP/F
Bolts installed and tensioned per specification Hold
P/F
Site welding completed per WPS Witness
P/F
Touch-up coating at connections complete✓
As-built survey completedReady to use this template?