Structural SteelCommercial
Structural Welding Inspection & Test Plan
Dedicated welding ITP for structural steel covering welder qualifications, WPS compliance, preheat requirements, visual inspection and non-destructive testing per AS/NZS 1554.
14 checklist items
3 hold points
2 witness points
Checklist Preview
Pre-Weld Checks
Requires sign-offP/F
Welder qualifications current for joint category Hold
P/F
Approved WPS available at workfaceP/F
Joint preparation per WPS (bevel, root gap)P/F
Preheat temperature achieved Witness
#
Measured preheat temperature (°C)P/F
Welding consumables per WPS (type and storage)During Welding
P/F
Interpass temperature within limitsP/F
Run sequence per WPSP/F
Back gouging where requiredPost-Weld Inspection
Requires sign-offP/F
Visual inspection per AS/NZS 1554 Table 8.1 Hold
P/F
Weld profile within acceptance criteriaP/F
Undercut within permissible limitsP/F
NDT (UT/MT/PT) results satisfactory Hold Witness
Aa
NDT report reference numberPrefer AI?
Generate a custom Structural Steel ITP in seconds
Describe your scope and our AI builds a complete ITP with hold points, witness points, and sign-off roles — tailored to your project.
Free AI ITP Generator →Ready to use this template?
Sign up, import this ITP template into your project, and start inspecting. 14 days free — no credit card required.
Get started free