Structural Welding Inspection & Test Plan
Dedicated welding ITP for structural steel covering welder qualifications, WPS compliance, preheat requirements, visual inspection and non-destructive testing per AS/NZS 1554.
14 checklist items
3 hold points
2 witness points
Checklist Preview
Pre-Weld Checks
Requires sign-offP/F
Welder qualifications current for joint category Hold
P/F
Approved WPS available at workfaceP/F
Joint preparation per WPS (bevel, root gap)P/F
Preheat temperature achieved Witness
#
Measured preheat temperature (°C)P/F
Welding consumables per WPS (type and storage)During Welding
P/F
Interpass temperature within limitsP/F
Run sequence per WPSP/F
Back gouging where requiredPost-Weld Inspection
Requires sign-offP/F
Visual inspection per AS/NZS 1554 Table 8.1 Hold
P/F
Weld profile within acceptance criteriaP/F
Undercut within permissible limitsP/F
NDT (UT/MT/PT) results satisfactory Hold Witness