Planter Box Waterproofing Inspection & Test Plan
ITP for planter box waterproofing on podium and rooftop structures covering internal lining, root barriers, drainage layers, overflow provisions and long-term maintenance considerations.
12 checklist items
2 hold points
1 witness points
Checklist Preview
Substrate Preparation
Requires sign-offP/F
Concrete fully cured and surface preparedP/F
Internal corner fillets installedP/F
Drain outlet pre-formed and preppedWaterproof Lining
Requires sign-offP/F
Membrane system rated for permanent immersion Hold
P/F
Membrane continuous to top of planter wallP/F
Reinforcing band at all corners and junctionsPhoto
P/F
Root barrier layer installed over membraneDrainage & Testing
Requires sign-offP/F
Drainage cell layer installed at baseP/F
Geotextile filter layer over drainage cellsP/F
Overflow outlet at correct heightP/F
Flood test satisfactory (48-hour minimum) Hold Witness
P/F
Inspection access for drain maintenance notedPrefer AI?
Generate a custom Waterproofing ITP in seconds
Describe your scope and our AI builds a complete ITP with hold points, witness points, and sign-off roles — tailored to your project.
Free AI ITP Generator →Ready to use this template?
Sign up, import this ITP template into your project, and start inspecting. 14 days free — no credit card required.
Get started free